River Nile dam: Filling operation begins – Ethiopia

View of the dam construction siteImage copyright Getty Images
Image caption The dam’s construction, seen here in December 2019, began in 2011

Ethiopia has started filling the reservoir behind the disputed Grand Renaissance dam on the River Nile – a day after talks with Egypt and Sudan ended without agreement, officials say.

Ethiopian Water Minister Seleshi Bekele confirmed the latest satellite images showing water levels rising.

Ethiopia sees the hydroelectric project as crucial for its economic growth.

But Egypt and Sudan, which are downstream, fear the large dam will greatly reduce their access to water.

Years of fraught negotiations have failed to reach a consensus on how and when to fill the reservoir, and how much water it should release.

On Wednesday, Mr Seleshi told Ethiopian state broadcaster EBC that the filling operation had begun, adding: “The construction of the dam and the filling of the water go hand in hand.”

His comments come after satellite images taken between 27 June and 12 July show a steady increase in the amount of water being held back by the dam.

The images caused a wave of excitement in Ethiopia over the $4bn (£3.2bn) Grand Ethiopian Renaissance Dam (Gerd) project – but caused concern in Egypt.

Interactive A large reservoir is beginning to form behind the dam

12 July 2020

Satellite image showing the River Nile from above in northwestern Ethiopia, 12 July

26 June 2020

Satellite image showing the River Nile from above in northwestern Ethiopia, 26 June

When fully operational, the dam will become the largest hydro-electric plant in Africa, providing power to some 65 million Ethiopians, who currently lack a regular electricity supply. However, Egypt gets almost all of its water from the Nile and fears the dam will reduce supplies.

How will the dam be filled?

The minister’s announcement might give the impression that filling up the dam will be like filling up a bath – and Ethiopia can turn on and off a tap at will.

But the truth is that the rainy season, which began in June and lasts until September, will fill the dam naturally.

Given the stage that the construction is at “there is nothing that can stop the reservoir from filling to the low point of the dam”, Dr Kevin Wheeler, who has been following the Gerd project since 2012, told the BBC.

From the start of the process in 2011, the dam has been built around the Blue Nile as it continued to flow through the enormous building site.

The Gerd in construction

Reuters

The Grand Ethiopian Renaissance Dam

Africa’s biggest hydropower project

  • Construction beganon the Blue Nile in 2011

  • The $4bn costhas been partly met by citizens buying bonds

  • The power generatedwill transform the lives of millions of Ethiopians

  • Egypt is worriedas it almost entirely relies on the water from the Nile

  • It sits downstreamof the dam and wants a guaranteed flow of water

  • Negotiationshave so far failed to reach a deal on some key issues

Source: Reuters/BBC

Builders could work on the vast structures on either side of the river without any problem. In the middle, during the dry season, the river was diverted through culverts, or pipes, to allow that section to be built up.

The bottom of the middle section is now complete and the river is currently flowing through bypass channels at the foot of the wall.

As the impact of the rainy season begins to be felt at the dam site, the amount of water that can pass through those channels will soon be less than the amount of water entering the area, meaning that it will back up further and add to the lake that will sit behind the dam, Dr Wheeler said.

The Ethiopian authorities can close the gates on some of the channels to increase the amount of water being held back but this may not be necessary, he added.

You may also be interested in:

How long will it take to fill?

In the first year, the Gerd will retain 4.9 billion cubic meters (bcm) of water, taking it up to the height of the lowest point on the dam wall, allowing Ethiopia to test the first set of turbines. On average, the total annual flow of the Blue Nile is 49bcm.

In the dry season the lake will recede a bit, allowing for the dam wall to be built up and in the second year a further 13.5bcm will be retained.

By that time, the water level should have reached the second set of turbines, meaning that the flow of water can be managed more deliberately.

Explore the Nile with 360 video

a 360-degree version of the Damming the Nile VR series from BBC News

Media playback is unsupported on your device

Join Alastair Leithead and his team, travelling in 2018 from the Blue Nile’s source to the sea – through Ethiopia and Sudan into Egypt.

Ethiopia says it will take between five to seven years to fill up the dam to its maximum flood season capacity of 74bcm. At that point, the lake that will be created could stretch back some 250km (155 miles) upstream.

Between each subsequent flood season the reservoir will be lowered to 49.3bcm.

Egypt, which almost entirely relies on the Nile for its water needs, is concerned that in most years of the filling it is not guaranteed a specific volume of water.

And once the filling stage is over, Ethiopia is reluctant to be tied to a figure of how much water to release.

In years of normal or above average rainfall that should not be a problem, but Egypt is nervous about what might happen during prolonged drought.

Click Here to Visit Orignal Source of Article https://www.bbc.co.uk/news/world-africa-53416277

Related posts

Biden to unveil spending plan worth trillions

BBC News

‘I lost my home. The shock will never fully set in’

BBC News

US Election 2020: Trump and Obama lock horns in rival rallies

BBC News

This website uses cookies to improve your experience. We'll assume you're ok with this, but you can opt-out if you wish. Accept Read More

Privacy & Cookies Policy